~ We make Greater Boston Accessible ~
Emergency infrastructure repair contract in response to the City of Quincy’s declared State of Emergency due to coastal damage from March 2018’s Nor’easter Storm Riley. Focus of work was sidewalk and road repairs impacted by erosion damage and intent was to restore affected areas to pre-storm conditions. Project scope included road and sidewalk reconstruction around the Brook Meadows Elementary School including (12”) road reclaim, ADA sidewalks and pedestrian ramps, drywell and asphalt paving. Significant ADA sidewalk repairs were made along Sea Street, including erosion mitigation measures by installing geotextile fabrics in conjunction with (6”) rip-rap protection and controls.